SUGGESTED INSTALLATION SPECIFICATIONS
There should be a minimum of 36" clearance completely around the machine.
The vent piping should be a class A, UL Approved, 8" inside diameter. The temperature rating should be no less than 1,400 degress continuous duty and 2,100 degrees intermittent.
Electric requirements:
- The machine is fused with 20 amp. main fuses.
- A 30 amp. power source to the machine will be more than adequate.
- 220 volt, 3 prong grounded plug-in.
Gas line requirements:
- If not more than 30', 3/4" black gas piping will be adequate; otherwise, check with your local gas company. Tell them the actual footage from the meter to your new roaster and that you need to be able to operate an appliance that will consume 2lbs of gas per hour at 7 water inch columns of gas pressure.
The roaster should be bolted with 4 1/2' floor anchor bolts. A roped off or fenced in operating area is suggested.
NOTE: Skin surfaces of afterburner can reach temperatures of 150 degrees F.
Also note that all of Coffee PER, Inc. manufacturer's suggested installation requirements are just suggestions. All federal, state and local codes do take precedence over any of our suggested installation requirements.